Jaguar Mining Provides Q3 2009 Update of Operations

    
    Record Quarterly Output Up 19%, Turmalina Phase I Expansion Completed on
    Schedule

    JAG - TSX/NYSE
    

CONCORD, NH, Oct. 14 /CNW/ - Jaguar Mining Inc. ("Jaguar" or "the Company") (JAG: TSX/NYSE, JAG.NT: TSX) provided a summary today of its preliminary Q3 2009 operating performance. All figures are in U.S. dollars unless otherwise indicated. See recent operating highlights below.

    
    Consolidated Operations (Turmalina, Paciência and Sabara)

    -   In Q3 2009, the Company produced a record 41,585 ounces of gold at an
        average cash operating cost of $451 per ounce compared to 34,935
        ounces at an average cash operating cost of $461 per ounce during the
        same period last year, a production increase of 19%.

    -   For the first nine months of 2009, Jaguar produced 115,211 ounces of
        gold at an average cash operating cost of $444 per ounce compared to
        77,130 ounces at an average cash operating cost of $450 per ounce
        during the first nine months of 2008, a production increase of 49%.

    -   Excluding the Sabara operation, which was idled during August and
        September 2009 (See Sabara Operations below), Q3 2009 gold production
        increased 12% or by 4,370 ounces over Q2 2009 gold production.

    -   Q3 2009 gold sales rose to 36,314 ounces at an average price of $969
        per ounce, 21% above the comparable Q3 2008 gold sales of 29,926
        ounces at an average price of $862 per ounce.

    -   Although cash operating costs were lower than Q2 2009 and 2008, the
        further weakening of the U.S. dollar continued to impact reported
        cash operating costs. Exchange rates in Q3 2009 averaged R$1.87 per
        $1.00 compared to R$2.08 and R$2.32 per $1.00 in Q2 2009 and Q1 2009,
        respectively; an increase (of the Brazilian real) of 10% and 19%
        respectively. Had the Brazilian real remained steady at the R$2.08
        per $1.00 in Q3 2009, average cash operating costs would have been
        reduced to $406 per ounce compared to the reported $451 per ounce.

    -   In September, the Company completed the construction of the Phase I
        expansion at Turmalina to boost annual gold production capacity from
        80,000 ounces per year to 100,000 ounces per year. The new components
        are expected to reach design levels during October 2009.

    -   Underground mine development at operations in the Iron Quadrangle
        during Q3 2009 reached an all-time high record of 4.0 km in a
        quarter, bringing year-to-date development to 10.7 km and total in-
        place development to nearly 40 km. This amount of development helps
        ensure the Company's ability to convert resources into reserves on-
        schedule, as well as provide at least 18 months of advanced mine
        access.

    -   Management currently estimates FY 2009 gold production will range
        between approximately 165,000 to 170,000 ounces at average cash
        operating costs of between $444 and $452 per ounce. The decision to
        idle Sabara in Q1 and most of Q3 2009 accounts for the reduction from
        the top-end of management's initial guidance of between 165,000 to
        175,000 ounces. The idling of Sabara for approximately half of the
        year also benefits Jaguar's overall cost performance.
    

Turmalina Operations - On Plan for Q3

In Q3 2009, Turmalina produced 22,249 ounces of gold at an average cash operating cost of $411 per ounce compared to 19,321 ounces at an average cash operating cost of $358 per ounce in Q3 2008.

    
    The following was achieved at Turmalina during Q3 2009:

    -   Mine production totaled 177,459 tonnes of ore at an average run-of-
        mine ("ROM") grade of 5.11 grams per tonne compared to 128,354 tonnes
        of ore at an average ROM grade of 5.20 grams per tonne in Q3 2008.

    -   Ore processed through the mill totaled 153,324 tonnes at an average
        feed grade of 5.27 grams per tonne compared to 128,041 tonnes at an
        average feed grade of 5.42 grams per tonne in Q3 2008.

    -   The plant recovery rate averaged 89%.

    -   Mine development totaled 1.25 km.

    -   Installed underground development within the Turmalina mine is
        adequate to achieve the mine plan for a period of 18 months.

    -   Construction of the Phase I expansion circuit to boost annual gold
        production from 80,000 ounces per year to 100,000 ounces per year was
        completed on-schedule. The new circuit was placed into operation on
        October 5, 2009.
    

Paciência Operations - On Plan for Q3

In Q3 2009, Paciência produced 17,927 ounces of gold at an average cash operating cost of $468 per ounce compared to 10,640 ounces at an average cash operating cost of $523 per ounce during Q3 2008.

    
    The following was achieved at Paciência during Q3 2009:

    -   Steps initiated in Q3 2009 to increase ore output and limit dilution
        at the St. Isabel mine yielded positive results with ore production
        rising to 131,909 tonnes at an average ROM grade of 3.54 grams per
        tonne compared to 107,862 tonnes at an average ROM grade 3.19 grams
        per tonne in Q2 2009.

    -   Ore shipments from the Pilar mine continued during Q3 2009 at
        approximately the same level as Q2 2009 (40,912 tonnes at an average
        ROM grade of 4.32 grams per tonne versus 40,458 tonnes at an average
        ROM grade of 4.36 grams per tonne in Q2 2009).

    -   The initial shipments of ore from the Palmital mine (conglomerates)
        near the Paciência plant began in Q3 2009 where ore production
        totaled 6,745 tonnes at an average ROM grade of 6.99 grams per tonne.

    -   Consolidated ore production for the Paciência mining complex totaled
        179,566 tonnes at an average ROM grade of 3.84 grams per tonne
        compared to ore production of 96,020 tonnes at an average ROM grade
        of 3.32 grams per tonne in Q3 2008.

    -   Ore processed through the mill totaled 167,193 tonnes with an average
        feed grade of 3.55 grams per tonne.

    -   The plant recovery rate averaged 93%.

    -   Mine development at the St. Isabel mine totaled 1.0 km, 0.4 km at the
        Pilar mine, 0.3 km at Palmital and 0.5 km at the NW1 zone.
    

Management plans to continue ore shipments from the Pilar mine during Q4 2009. However, during the latter part of Q1 2010, management intends to divert ore from Pilar to the Caeté Plant under construction, which is expected to begin commissioning during Q2 2010. Gold production at Paciência should not be materially affected as increases in ore production from the St. Isabel mine, Palmital mine and NW1 zone are expected to offset the re-direction of Pilar ore and lead to lower cash operating costs.

Sabara Operations

The Company is conducting a strategic review of the Sabara mining concessions and leaching facility, which could include divesting the operation in its entirety before the end of 2010. As part of this strategic review, and to maximize cash flow from this operation until new higher-grade oxide resources are available, the crushing and leaching operations were idled during most of the quarter. Curtailing this operation was unplanned at the beginning of the quarter. Management determined the profitability of the operation was significantly reduced running at lower throughput rates with limited quantities of ore from the Serra Paraiso mine. With the addition of ore from a new oxide zone in development at the Roca Grande deposit in the Caeté region, management intends to re-start crushing and leaching operations at the Sabara plant during the fourth quarter of 2009.

Mining operations at the Zone A mine were terminated as expected in Q2 2009 due to exhaustion of mineral resources. Ore shipments from the Serra Paraiso mine to the Sabara leaching and processing site continued during Q3 2009 and will continue to be stockpiled until leaching operations recommence. Serra Paraiso produced 15,035 tonnes at an average ROM grade of 2.48 grams per tonne.

Caeté Project

Construction of Jaguar's new Caeté Project is on-schedule for completion in March/April 2010. The following milestones have been achieved per the project's schedule.

    
    -   Basic engineering is 100% complete with detailed engineering 68%
        concluded.

    -   All major equipment required for the project, including crushing and
        milling components, have been acquired.

    -   Crushing and Storage
        -  Civil works for the crushing circuit is 100% complete.
        -  Civil works for storage of crushed ore is scheduled to be
           completed late October.
        -  Steel fabrication for the primary and secondary crushing circuits
           is underway and will be completed by the end of the year.

    -   Milling
        -  Mill equipment is on-site.
        -  Installation is scheduled for Q1 2009.

    -   Carbon-in-pulp ("CIP")Processing Plant
        -  Major components are on-site.

    -   Tank fabrication for the leaching circuit is underway and will
        continue through year-end. Tailings Storage
        -  Construction began on July 1st and is expected to be completed by
           year-end.
        -  The liner for this structure will be installed in Q1 2010.

    -   All permits, licenses and power contracts necessary for mine
        development, and construction and commissioning of the operation have
        been received.
    

Cash Position

As of September 30, 2009, the Company held cash and cash equivalents of approximately $233.2 million. Approximately 40% of the Company's current cash position is held in Brazil and earns approximately 8.5% interest. The Company received net proceeds of $159.1 million during September from the issuance of senior convertible notes bearing a 4.5% coupon. Jaguar intends to redeem the outstanding Cdn.$86.25 million of 10.5% notes issued in 2007 before the end of Q1 2010.

2009 Outlook

The Company's 2009 production and cost estimates are as follows:

    
    -------------------------------------------------------------------------
                    Actual         Estimated          Actual       Estimated
    -------------------------------------------------------------------------
    Operation   Y-T-D 2009           FY 2009      Y-T-D 2009         FY 2009
                Production        Production  Cash Operating  Cash Operating
                       (oz)              (oz)     Cost ($/oz)     Cost ($/oz)
    -------------------------------------------------------------------------

    -------------------------------------------------------------------------
    Turmalina       60,887     87,000-90,000            $389        $389-396
    -------------------------------------------------------------------------
    Paciência       47,965     68,000-70,000            $482        $479-487
    -------------------------------------------------------------------------
    Sabara           6,360            10,000            $680        $650-666
    -------------------------------------------------------------------------
    Total          115,211   165,000-170,000            $444        $444-452
    -------------------------------------------------------------------------

    Note: Estimated cash operating costs based on R$1.75 to R$1.85 per $1.00.
    

Q3 Conference Call Details

The Company will release its Q3 2009 financial and operating results after the market close on November 9, 2009. The Company will hold a conference call the following morning, November 10 at 10:00 a.m. ET, to discuss the results.

    
    From North America:      800-218-5691
    International:           213-416-2192
    Replay:
    From North America:      800-675-9924
    International:           213-416-2185
    Replay ID:               111009
    Webcast:                 www.jaguarmining.com
    

About Jaguar

Jaguar is one of the fastest growing gold producers in Brazil with operations in a prolific greenstone belt in the state of Minas Gerais. Jaguar is actively exploring and developing additional mineral resources at its 93,000-acre land base in Minas Gerais and on an additional 182,000 acres in the state of Ceara in the Northeast of Brazil through a joint venture. The Company has no gold hedges in place thereby providing the leverage to gold prices directly to its investors. Additional information is available on the Company's website at www.jaguarmining.com.

Forward Looking Statements

This press release contains forward-looking statements, within the meaning of the U.S. Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws, concerning the Company's objectives, such as estimated 2009 gold production and cash operating costs, the build-out of the Caeté Project and lowering cash operating costs at Paciência. These forward-looking statements can be identified by the use of the words "intends", "plans", "expects", "expected" and "will". Forward-looking statements involve known and unknown risks, uncertainties and other factors, which may cause the actual results, or performance to be materially different from any future results or performance expressed or implied by the forward-looking statements.

These factors include the inherent risks involved in the exploration and development of mineral properties, the uncertainties involved in interpreting drilling results and other ecological data, fluctuating gold prices and monetary exchange rates, the possibility of project cost delays and overruns or unanticipated costs and expenses, uncertainties relating to the availability and costs of financing needed in the future, uncertainties related to production rates, timing of production and the cash and total costs of production, changes in applicable laws including laws related to mining development, environmental protection, and the protection of the health and safety of mine workers, the availability of labor and equipment, the possibility of labor strikes and work stoppages and changes in general economic conditions. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

These forward-looking statements represent our views as of the date of discussion. The Company anticipates that subsequent events and developments may cause the Company's views to change. The Company does not undertake to update any forward-looking statements, either written or oral, that may be made from time to time by or on behalf of the Company subsequent to the date of this discussion except as required by law. For a discussion of important factors affecting the Company, including fluctuations in the price of gold and exchange rates, uncertainty in the calculation of mineral resources, competition, uncertainty concerning geological conditions and governmental regulations and assumptions underlying the Company's forward-looking statements, see the "CAUTIONARY NOTE" regarding forward-looking statements and "RISK FACTORS" in the Company's Annual Information Form for the year ended December 31, 2008 filed on System for Electronic Document Analysis and Retrieval and available at http://www.sedar.com and the Company's Annual Report on Form 40-F for the year ended December 31, 2008 filed with the United States Securities and Exchange Commission and available at www.sec.gov.

%CIK: 0001333849

SOURCE Jaguar Mining Inc.

For further information: For further information: Investors and analysts: Bob Zwerneman, Vice President Corporate Development and Director of Investor Relations, (603) 224-4800, bobz@jaguarmining.com; Media inquiries: Valéria Rezende DioDato, Director of Communication, (603) 224-4800, valeria@jaguarmining.com


Custom Packages

Browse our custom packages or build your own to meet your unique communications needs.

Start today.

CNW Membership

Fill out a CNW membership form or contact us at 1 (877) 269-7890

Learn about CNW services

Request more information about CNW products and services or call us at 1 (877) 269-7890