Western Wind announces the status of its various projects and financing arrangements



    
    Toronto Venture Exchange Symbol: "WND"
    Issued and Outstanding: 36,703,251
    

    VANCOUVER, Jan. 15 /CNW/ - Western Wind Energy Corp. ("Western Wind") is
pleased to provide the following operational and corporate update.
    In June 2008, Western Wind entirely paid off its project debt on its
producing Mesa wind farm which is rated at 30 MW ("Megawatts"). Western Wind
now owns a fleet of over 500 wind turbines of which 460 are owned debt-free.
    Despite the market turmoil, we are focusing on capitalizing current
economical, environmental and political trends supporting the broad-based
alternative energy expansion strategy.

    
    Western Wind's Projects

    Western Wind owns or leases 27,733 acres in California and Arizona.
Details of the projects are:

    -------------------------------------------------------------------------
                                     Nameplate           Land
    Generating      Development       Capacity       Resource
    Facility              Stage            (MW)        (acres)         State
    -------------------------------------------------------------------------
    Mesa Wind Farm    Producing             30            440     California
    -------------------------------------------------------------------------
    Windridge Wind
     Farm             Producing            4.5            191     California
    -------------------------------------------------------------------------
    Windstar         Late-stage
     Project        development            120          1,606     California
    -------------------------------------------------------------------------
    Barstow Project Early-stage
                    development            100          3,300     California
    -------------------------------------------------------------------------
    Reef City       Early-stage
                    development             40          1,200     California
    -------------------------------------------------------------------------
    Steel Park       Late-stage
                    development             15          1,110        Arizona
    -------------------------------------------------------------------------
    Steel Park      Early-stage
     Expansion      development            200         19,051        Arizona
    -------------------------------------------------------------------------
    Howling Dog     Early-stage
                    development             15            393        Arizona
    -------------------------------------------------------------------------
    Red Lake        Early-stage
                    development             20            442        Arizona
    -------------------------------------------------------------------------
    (xx)   Estimated nameplate capacity for particular projects can
           increase or decrease based on the following risk factors: limiting
           construction factors, such as topography and geography; any future
           or unknown environmental uncertainties; changes in capital cost
           items; changes in projected operating and maintenance costs;
           ability to obtain project financing and market conditions in the
           debt and project equity markets; interest in power purchase
           entities to procure specific amounts of energy; changes in local
           zoning policies; and events of force majeure, such as earthquakes,
           landslides, etc.
    

    Western Wind is in the process of purchasing or leasing additional sites
with potential for solar and wind development in California and Ontario. For
competitive reasons, the details of proposed sites are withheld.

    Windstar Project, Tehachapi, California

    Site control

    Western Wind currently directly owns 1,606 acres of land in Tehachapi,
California, which depending on what turbine is selected, is sufficient to
build its 120 MW Windstar Project.
    Western Wind has also leased an additional 280 acres of land in
Tehachapi, which may be added to the Windstar Project.

    Transmission Access

    Western Wind has submitted the requisite transmission line applications
and expects to execute the transmission agreements in the near future. Western
Wind already has executed interconnection and transmission service agreements
for the privately owned Sagebrush Line. In accordance with the U.S. Federal
Energy Regulatory Commission rules, Western Wind must construct the Windstar
project by December 31, 2010 in order to maintain its current queue position
with the California Independent System Operator. As a safety measure, Western
Wind is seeking an extension on this date as a result of various delays in the
interconnection feasibility study process.

    Power Purchase Agreements

    Western Wind has a Power Purchase Agreement ("PPA") with the Southern
California Edison Company, which has been amended from time to time to extend
the commercial operation date. Currently, the PPA requires that the Windstar
Project be in commercial operation by December 31, 2009; however, the Company
is awaiting an approval from SCE for an amendment to extend the commercial
operation date to December 31, 2010. Western Wind may terminate the contract
if it cannot acquire turbines at specified prices; however, due to the
California Renewable Portfolio Standard requiring utility companies to meet
specified targets by specified deadlines, Western Wind expects to be in a
position to negotiate a new PPA if the price term in the existing PPA cannot
be adjusted. Western Wind is currently in negotiations with Southern
California Edison on a new pricing formula. The California Public Utilities
Commission has recommended that long-term prices for renewable projects in
California should be US $114 per megawatt hour for a 20-year contract and US
$119 per megawatt hours for a 25-year contract. This is in addition to the
inflation adjusted US $21 per megawatt hour Production Tax Credit.

    Zoning and Permits

    Western Wind has submitted to Kern County the required applications and
associated archeological and environmental reports and expects to receive
approval of its application for a zone change for the Windstar Project in the
next few months. In the fall of 2008, Kern County notified Western Wind that
the County will support the application as a mitigated Declaration of No
Significant Impact.

    Detailed Micro-Siting and Resource Assessment

    Western Wind's independent consulting meteorologist, Richard Simon, M.S.,
has completed detailed and definitive micro-siting and long term resource
assessment on the Windstar Project utilizing several major turbine models from
various bankable equipment manufacturers. The details of these assessments are
confidential but Western Wind is pleased with the results.

    Design and Engineering

    Upon receipt of the zoning change, Western Wind will submit the design
and engineering plans to Kern County to complete its building permit. The
information to be submitted typically includes, but is not limited to
engineered plot plans showing turbine locations, engineered structural
foundation design and drawings, engineered structural soil reports, civil
design drawings for roads and pads, and engineered substation design drawings.
If approval is received on or about March 2009, Western Wind projects that the
structural permit process can be completed and permits issued by February
2010.

    Long-lead items

    In its November 12, 2007 press release, Western Wind stated that delivery
of turbines was expected in late 2008 and commissioning expected in the second
quarter 2009. Upon securing financing, Western Wind will order turbines and
other electronic equipment or turbines will be provided by another party as
part of their participation in the project. Turbines must be delivered six
months prior to the anticipated completion date.

    Construction

    If the above timelines are met, construction is anticipated to begin in
December 2009 and be completed in October 2010. There have been delays in the
interconnection study process, the pricing re-negotiations with SCE and the
zoning process.

    Financing

    In anticipation of the approval of the zoning, price adjustment from SCE
and completion of interconnection agreements, Western Wind has begun
negotiations with various industry recognized project finance institutions,
both passive and non-passive. The projected cost to construct the entire
project is estimated, at this time, to be approximately US$280 million. Some
of the institutional investors with which Western Wind is in discussions, have
access to turbines, which would obviate the need to order turbines separately.
There is no guarantee that Western Wind will receive financing on acceptable
terms.

    Valuation of the Windstar Project

    In its May 21, 2008 news release, Western Wind announced that, although
it had received an offer of $228 million to purchase the Windstar assets,
Western Wind was still reviewing other options. The $228 million offer to
purchase Western Wind's Windstar Project assets was based on a $36 million
up-front payment on the commencement of construction and the balance of $192
million payable over the 30-year life of the lease, based on the value of a 7%
gross annual royalty from payments on the land, which would have been retained
by Western Wind and back-end bonus payments based on a confidential formula.
Western Wind has continued to discuss proposals from various parties,
consistent with the net present value of the above offer.

    Risks

    A detailed discussion of the general business risks and project
milestones are contained in Western Wind's Form 20-F filed with the SEC.

    Barstow Project, California

    On February 14, 2008, Western Wind announced that it had secured a new
100-megawatt wind energy and solar site near Barstow, California. Western Wind
has signed an agreement with the United States Bureau of Land Management
("BLM") to conduct all required environmental surveys to install
meteorological towers to complete detailed micro-siting of the wind resource
and to complete the installation of the towers. Detailed micro-siting is
scheduled to begin this spring. If Western Wind determines that the project
economics are sufficient to justify developing a project, it will conduct the
required environmental surveys to install wind turbines and towers and
associated electrical equipment and apply for a commercial right of way grant
from the BLM of approximately 3,300 acres. Western Wind is first in the queue
to obtain this right of way. This project is in the early stage of development
and Western Wind has not begun negotiations for a PPA or submitted
applications for interconnection and transmission or zoning and permitting.
The project was delayed by the review process of the Bureau of Land
Management.

    Mesa Wind Farm Repower Project, Palm Springs, California

    The Mesa Wind Farm is an operating 30 MW wind farm, located on
approximately 440 acres leased from the BLM. Western Wind has submitted an
application, including all required environmental and archeological studies to
the BLM to replace the existing wind turbines with newer turbines to increase
the total capacity of the wind farm to 50 MW. As an alternative to a repower
of the entire wind farm, Western Wind is considering using a portion of the
BLM right-of-way grant for a new 20 MW project. If the BLM approves the plan
to repower, expected by the end of February 2009, Western Wind will determine
whether to repower the entire project or add a new 20 MW project.

    Windridge Wind Farm, Tehachapi, California

    The Windridge Wind Farm is an operating 4.5 MW wind farm, located on 192
acres owned by Western Wind. Currently, the wind farm is operating below
capacity and Western Wind is exploring various options to replace the older
wind turbines with fewer new larger capacity turbines to reach the 4.5 MW
capacity. In its October 24, 2007 news release, Western Wind announced that
the U.S. Federal Aviation Administration ("FAA") had approved the installation
of three new wind turbines. The FAA has, however, indicated that the towers
cannot be higher than the current turbines which will make it difficult to
repower with new larger turbines. Western Wind may increase current capacity
by utilizing several models of smaller turbines.

    Solar Projects, Ontario, Canada

    Western Wind is has executed conditional purchase and sale agreements to
acquire land in Ontario for solar energy development. Western Wind has entered
into such agreements to purchase three (3) project sites. These agreements
will allow Western Wind to purchase the land if Western Wind determines to
move forward with the project. Western Wind has applied for interconnection
and transmission service for three (3) - 10 MW projects with the Ontario's
Independent Electricity System Operator and has completed system impact
studies on all three (3) projects, with positive results.

    Financial Updates

    Western Wind anticipates executing project finance term sheets on the
Windstar Project within Q1 2009 and will release the details, as soon as
possible.
    Western Wind is in the business of acquiring exceptional land sites,
capital and technology for the production of electricity from renewable
sources. Western Wind Energy conducts its operations through its wholly owned
subsidiaries in Arizona and California. Management of Western Wind Energy
includes individuals involved in the operations and ownership of utility scale
wind energy facilities in California since 1981.
    For more detailed information on the renewable energy industry, please
see Western Wind's Form 20-F filed with the United States Securities Exchange
Commission ("SEC"): www.sec.gov.

    
    ON BEHALF OF THE BOARD OF DIRECTORS

    "SIGNED"

    Jeffrey J. Ciachurski
    Chief Executive Officer
    

    Cautionary Note on Forward Looking Statements

    Certain statements included in this news release are forward-looking
statements, which are made pursuant to the "safe harbor" provisions of the
United States Private Securities Litigation Reform Act of 1995. They include
estimates and statements that describe the Company's future plans, objectives
and goals, including words to the effect that the Company or management
expects a stated condition or result to occur. When used herein, words such as
"expect", "estimate", "believe", "intend", "intent", "scheduled";
"projection"; "anticipate" and other similar expressions are intended to
identify forward-looking statements. In particular, statements relating to the
future revenues, profitability, cash flows, expenses, capital costs,
regulatory approvals, various zoning processes, delays in environmental impact
studies, delays in negotiating power purchase pricing, negotiations relating
to turbine supply agreements, terms of financing, construction and
commissioning are forward-looking statements. Such forward-looking statements
involve inherent risks and uncertainties and subject to other factors, many of
which are beyond our control that may cause the actual results or performance
to differ materially from those expressed or implied by such forward-looking
statements. Such factors include, among others, asset impairment, price
volatility, fluctuations in foreign exchange rates, economic and political
events affecting energy supply and demand, fluctuations in wind grade,
geological, operating and environmental risks, problems during the
development, construction and start-up phases of wind projects, inadequacy of
insurance, etc. For a more comprehensive review of risk factors, please refer
to the Company's most recent annual report under "Management's Discussion and
Analysis of Financial Results" and Form 20-F under "Risk Factors" on file with
the U.S. Securities and Exchange Commission and Canadian provincial securities
regulatory authorities filed on SEDAR at www.sedar.com. The Company disclaims
any obligation to update or revise any forward-looking statements whether
because of new information, events or otherwise. Readers are cautioned not to
put undue reliance on these forward-looking statements. Additional information
regarding the Company is included in the Company's filings with the Canadian
securities regulators and the United States Securities and Exchange
Commission, a copy of which is posted on the SEDAR website at www.sedar.com.





For further information:

For further information: Western Wind Energy Corp., 1326 - 885 West
Georgia Street, Vancouver, BC, V6C 3E8, Telephone: (604) 685-WIND (9463),
Facsimile: (604) 685-9441, www.westernwindenergy.com

Organization Profile

Western Wind Energy

More on this organization


Custom Packages

Browse our custom packages or build your own to meet your unique communications needs.

Start today.

CNW Membership

Fill out a CNW membership form or contact us at 1 (877) 269-7890

Learn about CNW services

Request more information about CNW products and services or call us at 1 (877) 269-7890