Update on Randle Reef Sediment Remediation Project

HAMILTON, ON, Feb. 13, 2015 /CNW/ - The Randle Reef project partners are pleased to inform the community that a path forward has been established for the project.

In the summer of 2014, extensive consultation occurred with industry experts to determine options to advance the project within the current budget envelope. After careful consideration of all information received from industry, the project partners have identified modifications to the current project design that should result in significant cost savings without compromising the environmental goals of the project. For example:

  • Additional sampling of the harbour bottom in and around the Engineered Containment Facility (ECF) footprint was completed in the summer and fall of 2014 and allowed dredging areas and volumes of contaminated sediments to be more precisely defined. These activities also confirmed the viability of the proposed modifications to the ECF;
  • The modified ECF will continue to contain Priority 1 and Priority 2 sediments, which are the most highly contaminated sediments at the site. A larger portion of the lesser contaminated sediments will now be capped in place using in situ capping. This will enable a reduction in dredging volumes and associated costs, as well as a reduction in the size of the ECF of approximately 15 per cent;
  • The overall length of the ECF has been shortened and the updated design has fewer right angles, which will make dredging and rock placement activities between the containment facility's inner and outer walls easier and faster;
  • Construction processes were also simplified to yield cost reductions associated with items such as material handling and installation of the steel walls.

With these modifications, the project's environmental objective will continue to be achieved. The Randle Reef project is a key initiative in restoring Hamilton Harbour and removing it from the list of Great Lakes Areas of Concern. The project partners remain committed to working together on this clean-up project and starting construction as quickly as possible.

Stage 1 of the project is expected to be re-tendered in early 2015. Work is expected to commence this year in Hamilton Harbour with the reconstruction of a dock wall adjacent to the ECF, to permit contaminated sediments to be removed from this area.

The Governments of Canada and Ontario, the City of Hamilton, the Hamilton Port Authority, U.S. Steel Canada, the City of Burlington, and Halton Region would like to thank everyone who participated in Industry Day in July, and in the follow-up one-on-one sessions held throughout the summer. The constructive feedback that we received was very helpful in determining a solution to quickly move the Randle Reef project forward.

 

SOURCE Environment Canada

Image with caption: "Modified Project Design, January 2015 (CNW Group/Environment Canada)". Image available at: http://photos.newswire.ca/images/download/20150213_C6851_PHOTO_EN_12130.jpg

For further information: Environment Canada : Media Relations, 819-934-8008; Ministry of the Environment and Climate Change : Kate Jordan, Communications, 416-314-6666; City of Hamilton : Mike Kirkopoulos B.Sc., M.A., Director, Communications City Manager's Office, Tel.: 905-546-2424, ext. 2261, Cell.: 905-973-2314;Hamilton Port Authority : Larissa Fenn, Manager, Public Relations & Communications, 905-525-4330, ext. 235; City of Burlington : Donna Kell, Manager of Communications, Office: 905-335-7600, ext. 7841, Mobile: 905-630-6263; U.S. Steel Canada : Trevor Harris, Director, Government and Public Affairs, 905-577-4447; Environment Canada's Twitter page; Environment Canada's Facebook page

RELATED LINKS
http://www.ec.gc.ca

Custom Packages

Browse our custom packages or build your own to meet your unique communications needs.

Start today.

CNW Membership

Fill out a CNW membership form or contact us at 1 (877) 269-7890

Learn about CNW services

Request more information about CNW products and services or call us at 1 (877) 269-7890