/R E P E A T -- Deck replacement of the access ramp to Ile Sainte-Hélène from the Jacques-Cartier Bridge/



    LONGUEUIL, QC, March 28 /CNW Telbec/ - The Jacques Cartier and Champlain
Bridges Incorporated wishes to inform the public that the upstream access ramp
to Ile Sainte-Hélène from the Jacques-Cartier Bridge (south bound traffic)
will be closed for a deck replacement project that will last from Monday,
March 31 to Tuesday, May 27, 2008.
    The work consists generally in the replacement of 815 m2 of roadway deck
at a cost of $ 2 137 584,60.
    Bridge users are invited to follow the signage and detours that will be
put in place during for the construction period.
    Once the adjacent cycling path and sidewalk are opened in the spring
(based on weather conditions), both will remain opened throughout the
construction period.




For further information:

For further information: André Girard, Vice-president, Communications,
(450) 468-5775, andre.girard@pontsfederaux.ca; Source: Glen P. Carlin, Eng,
General Manager, The Jacques Cartier and Champlain Bridges Incorporated

Organization Profile

The Jacques Cartier and Champlain Bridges Incorporated

More on this organization


Custom Packages

Browse our custom packages or build your own to meet your unique communications needs.

Start today.

CNW Membership

Fill out a CNW membership form or contact us at 1 (877) 269-7890

Learn about CNW services

Request more information about CNW products and services or call us at 1 (877) 269-7890