Metanor - Update of the Work Completed on the Barry and Bachelor Properties



    TSX VENTURE EXCHANGE =MTO
    60,800,974 shares

    VAL-D'OR, QC, Nov. 8 /CNW Telbec/ - Metanor Resources Inc. (MTO: TSX-V)
is pleased to provide an update of the work carried out on the Barry and
Bachelor properties located in the north of Quebec, and comments on the
recommendations from the Preliminary Economic Study carried out by Géostat
International Inc. (Press release of October 30, 2007).
    In spring 2007, Géostat International Inc, was retained by Métanor to
prepare an economic study whose objective was to evaluate the economic
potential to exploit the deposit of Barry by open-pit mine and using the
rehabilitated mill at Bachelor. This economic study, whose results are
positive, was initiated last spring and was delivered to Métanor October 16,
2007.
    During the preparation of this study, the majority of its final
recommendations were already being carried out by Métanor who invested close
to $12M on the rehabilitation of the Bachelor Mill and the preparation of Bulk
Sampling at Barry.

    The work executed so far by Métanor at Bachelor and Barry includes:

    
    - The Repair of the External Infrastructure of the Bachelor Mill,
      including the coating and the insulation, which was completed a few
      months ago.
    - The Restoration of the Components of the Bachelor Mill (mechanical and
      electrical) is 95% completed. Métanor has even begun the commissioning
      of the internal components of the initial circuit of the mill made up
      of the crushers, ball mill and the conveyors bringing the material
      towards the ore bin.
    - On the Barry Property, the Preparation of the Site and the Installation
      of Surface Buildings (Service, warehouse, etc) are completed. The
      original stripped zone was extended significantly and Bulk Sampling has
      been underway for a few weeks. The first blasts made it possible to
      establish the starting point of Bulk Sampling and other blasts of mill
      feed are regularly being carried out. The broken ore is crushed
      immediately and stored on the site.
    - The Repair work of the road connecting Bachelor to the Barry site
      (which uses the principal roads of Domtar) is finished and is ready for
      the transport of the mill feed.
    

    This study depicts a scenario of operation with very conservative
parameters such as only 63% of the total resources were used in its
calculation. Further, this economic study's income was calculated using a
price of $660 CAD/oz and still shows positive conclusions as to the
profitability of the project.

    Other factors not taken into consideration in this study include:
    The potential resources were evaluated by InnovExplo inc., in a NI 43-101
technical report, dated of October 31, 2005 as follows: measured and indicated
resources of 841,591 t at 7.79 g/t Au (or 210,857 oz of gold) and inferred
resources of 426,148 t at 6.52 g/t Au (or 89,366 oz of gold). Several
mineralized zones were not included in the study: zone A and C of Bachelor
property, and the zones A and B as well as portions of the East Zone and the
West Zone of Hewfran property. From a total of 212,300 T of measured resources
calculated by Innovexplo in 2005 at Bachelor, only 84,477 T (40%) were used.
Therefore, a greater total of 477,930 T (110,298 ounces of gold) representing
37% of the total resources was not used at the time of this study.
    During the preparation of this study, Métanor repurchased 7% of the NSR
from Murgor on the Barry deposit (Press release of September 6, 2007), and
this was not factored in this study.
    The study used very high costs of operation however most of these costs
will be decreased. For example, this study uses 27 peoples that would be
necessary to operate the mill but Métanor budgets only 15 due to automation,
this represents an appreciable savings. A feasibility study has not yet been
completed and there is no certainty the company's projections will be
realized.
    At the time of this study, Métanor had just completed a $20M financing
which has been used for development work carried out until now on the
2 properties. As stated in Geostat's economic study of the Barry-Bachelor
project, the project will generate a cumulative operating cash flow of $6.5M
over 7 years. During spring 2007 the Company repurchased NSR's that will
create savings of $3M thus increasing the operating cash flow of the same
amount. Furthermore, the Company was successful in raising over $20M in fiscal
year 2006-2007, this amounts was not taken into consideration in the Geostat
economic study and will increase Metanor's cash flow.
    Considering all of the above factors and that the Geostat study used a
gold price of $660 CAD versus the current higher price suggests that the cash
flow could be significantly higher.
    Additionally, the recovery of further resources that were not used
(477,930 T containing approximately 110,298 ounces of gold), assuming the same
operating costs, would increase mine life and total cash flow.
    Mr. André Tremblay, P Eng. is the qualified person pursuant to National
Instrument 43-101 and supervised the technical information presented in the
news release.

    The TSX Venture Exchange does not accept any responsibility for the
    adequacy or the accuracy of the press release.




For further information:

For further information: Serge Roy, President, (819) 825-8678, Fax.:
(819) 825-8224, info@metanor.ca, www.metanor.ca; Renmark Financial
Communications Inc.: Jason Roy: jroy@renmarkfinancial.com; Jen Power:
jpower@renmarkfinancial.com, (514) 939-3989, Fax: (514) 939-3717,
www.renmarkfinancial.com

Organization Profile

METANOR RESOURCES INC.

More on this organization


Custom Packages

Browse our custom packages or build your own to meet your unique communications needs.

Start today.

CNW Membership

Fill out a CNW membership form or contact us at 1 (877) 269-7890

Learn about CNW services

Request more information about CNW products and services or call us at 1 (877) 269-7890