Bonaventure Expressway: Major maintenance work in 2011 - Major work from May to October at Exit 2 (Pierre-Dupuy Avenue)

LONGUEUIL, QC, May 4 /CNW Telbec/ - The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) wishes to announce major maintenance work on the Bonaventure Expressway from May to October. Note that the Bonaventure Expressway was built in 1966, and that a major facelift is today required.

The rehabilitation work of the deck, piers, concrete beams, the replacement of the roadway expansion joints and the pavement will begin on Friday, May 6 on the Bonaventure Expressway, in the Pierre-Dupuy Avenue sector (Exit 2 on the Bonaventure Expressway). The work will require several partial and complete closures of the Bonaventure Expressway at Exit 2, at night during the week and on week-ends, until mid-October.

The first required complete closure of the Bonaventure Expressway in both directions will take place according to the following schedule:

  • Friday, May 6, 11 PM to Monday, May 9, 5 AM.

Detour roads have been planned for the traffic in the work area. Please consult our map (http://bit.ly/bplZzT) for the different closing scenarios. In this case, it is a closure of type C.

Details of this closure:

Complete closure of the Bonaventure Expressway going east (Champlain Bridge) and west (Downtown Montreal) at Exit 2 including:

  1. Closing of the Wellington St. on ramp
  2. Complete closure of Pierre-Dupuy Ave. under the Bonaventure Expressway
  3. Closing of one of two lanes on Pierre-Dupuy Ave. going south and on Des Irlandais Street going north

For more information regarding the road work, or to consult our maps, please visit the Champlain Bridge area blog: www.champlainbridge.ca.

SOURCE THE JACQUES CARTIER AND CHAMPLAIN BRIDGES INCORPORATED

For further information:

Jean-Vincent Lacroix
Chief, Communications
The Jacques Cartier and Champlain Bridges Incorporated (JCCBI)
Tel.: 450 651-8771 ext. 232
Cellular: 514 249-1940
jlacroix@pjcci.ca

André Girard
Vice-President, Communications
The Federal Bridge Corporation
Tel.: 450 468-5775
andre.girard@pontsfederaux.ca

Profil de l'entreprise

THE JACQUES CARTIER AND CHAMPLAIN BRIDGES INCORPORATED

Renseignements sur cet organisme

THE FEDERAL BRIDGE CORPORATION LIMITED

Renseignements sur cet organisme


FORFAITS PERSONNALISÉS

Jetez un coup d’œil sur nos forfaits personnalisés ou créez le vôtre selon vos besoins de communication particuliers.

Commencez dès aujourd'hui .

ADHÉSION À CNW

Remplissez un formulaire d'adhésion à CNW ou communiquez avec nous au 1-877-269-7890.

RENSEIGNEZ-VOUS SUR LES SERVICES DE CNW

Demandez plus d'informations sur les produits et services de CNW ou communiquez avec nous au 1‑877-269-7890.